Dynacor Feeds First Ore to Ecuador Mill

MONTREAL, Nov. 02, 2026 (GLOBE NEWSWIRE) -- Dynacor Group Inc. (TSX: DNG) (“Dynacor” or the “Corporation”) is pleased to update on its Svetlana plant in Ecuador as it advances towards production restart. Svetlana was over 80% complete as at September 30, and on budget.

Dynacor has been informed of extended delivery timelines for the Svetlana cyclone cluster and additional refurbishment requirements for the elution and refinery circuit. As a result, Dynacor expects a short delay in the hot commissioning and ramp-up of the Svetlana plant. All other critical areas of the plant rehabilitation and restart are progressing to plan including:

  • First ore crushed – First ore was fed through the crushing circuit at end of October.
    • Crushing plant is being commissioned on sterile rock before transitioning to low-grade ore.
  • Commissioning is underway – Dry commissioning is ongoing in the crushing, grinding and leaching circuits and will commence in the other circuits over the coming weeks.
    • Hot commissioning is scheduled for December, followed by plant ramp-up in Q1 2027.
    • First gold pour is expected in January.
  • Plant rehabilitation is 82% complete and on budget.
    • Refurbishment of the main equipment in the crushing, grinding and leaching areas is complete.
    • On budget – As of September 30, 2026, approximately US$10.7 million had been spent (and US$4 million committed) of the US$22-$25 million projected capital expenditure for 2026.
    • Tailings – The working tailings storage facility is now operational.
  • Growing supplier pool– To accelerate the plant ramp-up, Dynacor plans to source ore from permitted artisanal and small-scale miners (ASMs) through the following:
    • Svetlana purchasing department – The internal purchasing team is in discussions with individual ASM suppliers close to Portovelo, a hub for ore processing in the region.
    • Partnership with planetGold - Under the recently signed collaboration agreement, planetGold will select and refer ASMs enlisted in its Ecuador program to Svetlana who, in turn, will evaluate them and their ore for formalised, mercury-free processing. Initially, this will give Svetlana access to 25-50 ASM suppliers.
      Led by the United Nations Environment Programme, planetGOLD works globally to make ASM practices safer, cleaner and more profitable.
    • Additional initiatives are underway to increase access to formalised ASM groups.
  • Regulatory – Dynacor’s commercialisation permit is expected to be issued by Ecuador’s MAE (Ministry of Environment and Energy) in the first week of November 2026.
    • The Corporation continues to advance its application for an Investment Protection Agreement (IPA), most recently through in-person negotiations with the Ministry of Production, Foreign Trade, Investments, and Fisheries.
  • Phased restart - Svetlana operations are initially being launched at 300 tonnes per day (tpd), before being ramped up to 500 tpd.

Daniel Misiano, President & CEO of Dynacor, stated: “While there has been a slight delay in hot commissioning, all critical aspects of the Svetlana restart are advancing as planned, the first ore milestone has been reached, and the project remains on budget. Importantly, we are on track for a strong restart due to the supplier network that is being put in place. We look forward to building on these achievements through continuing to advance to first gold and commercial production.

“Svetlana is a transformational asset for Dynacor that, when ramped up, will drive material production growth and margin expansion. Each milestone completed brings us closer to that growth.”

Figure 1 – Hopper loading ore into Svetlana's crushing circuit

Figure 1 – Hopper loading ore into Svetlana's crushing circuit

Figure 2 – CEO Daniel Misiano, and Galo García, Ecuador’s Deputy Minister of Mines, sign the planetGOLD collaboration agreement

Figure 2 – CEO Daniel Misiano, and Galo García, Ecuador’s Deputy Minister of Mines, sign the planetGOLD collaboration agreement

Q3-2026 Results

Dynacor expects to report third-quarter 2026 financial and operational results on and about November 12, 2026.

About Dynacor

Dynacor Group is an ore processing company dedicated to producing gold sourced from artisanal miners. Since its establishment in 1996, Dynacor has pioneered a responsible mineral supply chain with stringent traceability and audit standards for the fast-growing artisanal mining industry. By focusing on formalized miners, the Canadian company offers a win-win approach for governments and miners globally. Dynacor operates the Veta Dorada plant and owns a gold exploration property in Peru. The company is expanding to West Africa and within Latin America.

The premium paid by luxury jewellers for Dynacor’s PX Impact® gold goes to Fidamar Foundation, an NGO that mainly invests in health and education projects for artisanal mining communities in Peru. Visit www.dynacor.com for more information.

Forward-Looking Information

Certain statements in the preceding may constitute forward-looking statements, which involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of Dynacor, or industry results, to be materially different from any future result, performance or achievement expressed or implied by such forward-looking statements. These statements reflect management’s current expectations regarding future events and operating performance as of the date of this news release.

Contact:

For more information, please contact:

Ruth Hanna
Director, Investor Relations
T: 514-393-9000 #236
E: investors@dynacor.com
Website: https://dynacor.com

Renmark Financial Communications Inc.
Bettina Filippone
T: (416) 644-2020 or (212) 812-7680
E: bfilippone@renmarkfinancial.com  
Website: www.renmarkfinancial.com

Photos accompanying this announcement are available at 
https://www.globenewswire.com/NewsRoom/AttachmentNg/a8745862-c503-4dd3-b0b3-c451b3b8ceab
https://www.globenewswire.com/NewsRoom/AttachmentNg/77f517ae-28d8-4a14-a8d1-5e29fb5983e4


Primary Logo

Figure 1

Hopper loading ore into Svetlana's crushing circuit
Figure 2

CEO Daniel Misiano, and Galo García, Ecuador’s Deputy Minister of Mines, sign the planetGOLD collaboration agreement

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

Andorra Industry Press

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.